Decision details

Ashbridge, Ashmill & Cosway sites - settlement of the main construction contract final account with Geoffrey Osborne Limited

Decision Maker: Cabinet Member for Climate Action, Regeneration and Renters, Cabinet Member for Finance and Council Reform

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Settlement of main construction contract account

Decision:

Summary of Decision

The Cabinet Member for Finance and Council Reform and the Cabinet Member for Climate Action Regeneration and Renters in consultation with the Cabinet Member for Housing Services have:

 

·       Approved the additional £7,760,002 variance sum to the signed construction contract between the Council and Geoffrey Osborne Limited. The interim final account for the works delivered and agreed with the contractor amount to £51,250,000 (excluding VAT).

 

·       Approved the additional spend of £8.8m against the previously approved spend set out in the FBC to complete the scheme.

 

·       Noted the increase in budget requirement of £4.347m above existing provision which will be funded from the Affordable Housing Fund.

 

Reasons for Decision

The project is approaching the practical completion stage and under the construction contract, a final account statement is required to be agreed and signed between the Council and Osborne.

 

Publication date: 13/09/2023

Date of decision: 13/09/2023

Effective from: 21/09/2023