Decision Maker: Cabinet Member for Housing Services
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Direct award to undertake surveys of high rise blocks in line with the Building Safety Act.
Summary of Decision
The Cabinet Member for Housing Services has approved:
1. The direct award for Structural Survey Services to Ridge and Partners LLP.
2. The estimated cost for Stages 1 & 2 - £370,35 (including VAT), of which the cost to Council will be £219,851, including £19,026 unrecoverable leaseholder costs (including VAT) and the cost to leaseholders will be £150,500
3. That works can proceed without leaseholder consultation, limiting leaseholder contribution to £250 per leasehold property.
Reasons for Decision
The Council is required to conduct structural surveys to higher risk, high-rise buildings within Westminster’s Housing portfolio in line with the Building Safety Act 2022.
This paper requests approval of a direct award to Ridge and Partners LLP to carry out those surveys, as well as estimated costs and that works can proceed without leaseholder consultation.
Publication date: 14/03/2024
Date of decision: 14/03/2024
Accompanying Documents: