Decision details

Request for approval for Various Prevention Supported Housing Contracts: Direct award contract extensions and future procurement strategy

Decision Maker: Cabinet Member for Hsg Services

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: Yes

Purpose:

Cabinet Member approval sought for contract extensions.

Decision:

1.            That this report be exempt from disclosure by virtue of the Local Government Act 1972 Schedule 12A, Part 1, paragraph 3 (as amended), in that it contains information relating to the financial or business affairs of any particular person (including the authority holding that information).

 

2.         That the Cabinet Member for Housing Services approved a waiver of the Procurement Code to permit the direct award of interim contracts for the contracts listed in Appendix 1 of the report, for the total sum detailed in the report for the period 1st April 2018 to 31st March 2021 and noted that this will allow for a programme to be developed and implemented for the re-procurement of these services over the next two years.

 

Reasons for Decision 

1.            Regulation 72 (1) of the Public Contract Regulations 2015 require that for any variation clauses to be lawful they must be couched in ‘clear, precise and unequivocal’ terms, that state the scope and nature of possible modifications. The ‘review clauses’ in many of the existing contracts that enable the contracts to be rolled on without limit would therefore not be considered lawful. The contracts must be put onto a compliant contractual footing with clear start/expiry dates and provisions to extend that do not continue indefinitely.

2.            The current ‘expiry date’ for these services as set out in Appendix 1 of the report varies; many are 31st March 2019 and further extensions to the contracts are therefore sought to maintain continuity of service whilst a re-procurement programme is developed in order to achieve full compliance.

3.            At present, all the contracts are closely monitored and, as recorded in capitalesourcing, are considered to meet the Contract Managers’ expectations.

Publication date: 22/03/2019

Date of decision: 22/03/2019

Effective from: 30/03/2019