Issue - decisions

Strand/Aldwych project - vision, objectives and next steps

13/09/2018 - Strand/Aldwych project - vision, objectives and next steps

1.         Decision

 

1.1       That formal approval was given:

 

  • for the vision and objectives of the project
  • for the emerging concept design and its development to the next design stages
  • to undertake public consultation on the concept design

·         to proceed with Initial and Detailed Design following consultation

 

 

2.         Reason for Decision

 

2.1       A Cabinet Member decision was required to move forward the project to the next stages.  A concept design had been developed through the Feasibility Stage of the project and, whilst validated by the technical studies undertaken to date and stakeholder involvement, the design must now be shared with a wider audience and feedback sought from the community.  This is key to informing the next design stages.